What is proposed
The Energy Corporation of NSW (EnergyCo), a state statutory authority, is the proponent. The project would build new dual 500 kV lines from the New England Renewable Energy Zone south to the existing Bayswater Power Station, and 500 kV and 330 kV lines linking five energy hubs, where future wind, solar and storage projects would connect. It also includes a maintenance facility at Nemingha, near Tamworth, access tracks and road upgrades, and five temporary workforce camps. The executive summary puts the length at about 300 kilometres, across eight council areas: Armidale Regional, Uralla, Tamworth Regional, Walcha, Liverpool Plains, Upper Hunter, Muswellbrook and Singleton.
Construction is planned to start in 2028 and take about six years. The first stage, 2.4 GW of transfer capacity, would be energised in 2032 and the second, a further 3.6 GW, in 2034, for 6 GW in all. The NSW Government has declared it critical state significant infrastructure, so the Minister for Planning and Public Spaces decides it. It is also a controlled action under the Commonwealth's environment law (EPBC 2025/10405), for listed threatened species and communities, so the federal environment minister must approve it too.
Where it runs in New England
The EIS places the five hubs here:
- North Hub, a 330 kV switching station off Romani Road, Boorolong, in Armidale Regional, about 16 km north-west of Armidale.
- Central Hub A, a 500/330 kV substation off Glenburnie Road, Kentucky, on the Tamworth Regional and Uralla border, about 16 km south-west of Uralla.
- Central Hub B, a 500/330 kV substation off Thunderbolts Way, about 7 km south of Uralla.
- East Hub, a 330 kV switching station off Hillview Road, Salisbury Plains, about 13 km south-east of Uralla.
- Central South Hub, a 500/330 kV substation off the Oxley Highway at Walcha Road, about 13 km west of Walcha.
From Central South Hub the dual 500 kV line heads south towards the Hunter. The executive summary lists Woolomin, Dungowan, Rouchel, Gundy, Waverly, Barry and Niangala among the places where the corridor was moved or refined in response to community concerns, and the line would need a permanent easement through Nundle State Forest. The two largest workforce camps, about 550 workers each, would sit at Central South Hub and Central Hub A. The EIS estimates a peak construction workforce of about 1,400 people.
Who gets paid
Land for the easement would be bought by agreement where possible, and compulsorily under the
Land Acquisition (Just Terms Compensation) Act 1991 where not. The EIS counts 138 landholders on the
easement and access tracks, and seven whose land would be acquired outright for the hubs. On top of
compensation it offers strategic benefit payments to private landholders on which the transmission infrastructure would be located
:
$200,000 a kilometre, paid in instalments over 20 years from the start of operationsA.
Exhibit A · from the source
Neighbours are treated differently. The social impact assessment, in chapter 10 of the EIS,
rates each impact before and after mitigation for each group it affects. For the
Inequitable distribution of project impacts
,
it rates the effect on proximal landholders, the people near the line but not on it, at A/4, very
high, the top of its scale. The measures it lists for them are technical management measures, an
updated engagement plan and a place manager. The strategic benefit payment appears against the next
row, for the landholders who host the lineB. After those
measures it expects the neighbours' rating to fall to medium.
Exhibit B · from the source
The wider community fund sits outside the project. The EIS points to EnergyCo's Community and
Employment Benefit Program, funded by fees from generators in the REZ access scheme, with an initial
$60 million announced in May 2026. Its own table describes that money as
delivered separately by EnergyCo in its role as Infrastructure Planner under the EII Act (not as part of this project)
.
The state's benefit-sharing guideline, which sets rates for solar and wind farms, does not set one
for transmission. It says While this guideline does not apply, benefit-sharing is strongly encouraged
.
Tamworth's draft contributions policy names transmission among the projects it would cover, as
we reported on 4 November.
What the EIS says about the impacts
These are the EIS's own findings, in its executive summary, and they are the assessment the department will test.
- Bush and threatened species. About 3,203 hectares of native vegetation would be directly affected, including White Box, Yellow Box, Blakely's Red Gum grassy woodland and New England Peppermint woodland, both critically endangered. It counts up to 36 threatened plant and 35 threatened animal species, partly on assumed presence where surveyors could not get onto land. Residual impacts would be offset.
- Views. Of 57 homes and other private receivers near the line but off the easement, 9 rate a high or moderate visual impact and need mitigation; the four high ones are near Rouchel Brook in the Upper Hunter. One public viewpoint, on Niangala Road about 17 km south-west of Walcha, rates moderate. Homes on the easement are not assessed for views, because those landholders are compensated.
- Noise. In light rain or mist, corona noise from the lines is predicted to exceed the strictest night-time trigger at 48 homes closest to the line; for 23 of them the excess is under 2 dBA. Construction traffic on local roads would exceed the road noise criteria at 111 homes without mitigation.
- Traffic. The EIS calls the construction increase material but temporary and localised, with targeted intersection upgrades rather than network-wide works.
- Bushfire. It says
There are no records of a 500 kV transmission line starting a fire in Australia
, and that the lines would be unlikely to have any material effect on fire authorities' ability to suppress fires. - Community. Its social assessment finds attitudes are mixed, and that
communities perceive that adverse impacts, particularly for rural landholders, are concentrated, while benefits are uncertain or not equitably shared
.
Two camp sites are not assessed. A camp at Barry was found in May 2026, after most technical studies were done, and an alternative to the Muswellbrook camp is being investigated; both are left to a later Amendment Report.
Our view
The EIS is candid about who carries the load. Its own social assessment gives neighbours the highest rating on its scale for bearing an unfair share, and then attaches the money to the row below, for the landholders who host the line. That $200,000 a kilometre is real and it is sizeable, but it follows the easement, not the view, the noise or the construction traffic, all of which reach homes off it: the 9 receivers needing visual mitigation, the 48 homes in the corona noise prediction and the 111 on local roads. The community fund the EIS points to is outside the project, and the state guideline that sets rates for wind and solar does not set one for transmission. If you live near the corridor but not on it, the exhibition is the place to say what you think you are owed, and the department should ask EnergyCo to say what a neighbour gets. We asked EnergyCo that question on 14 November, and will publish its answer as given, or say if none arrives.
How to make a submission
Submissions close on Thursday 26 November. The extended notice says
The exhibition has been extended until Thursday 26 November 2026
.
All submissions must be made online through the project's Planning Portal page:
choose Make a submission and log in or create an account. You need your name and address, a
statement of whether you support, object or are commenting, your reasons, and a declaration of
any reportable political donations in the past two years. Submissions are published; you can ask
for your name to be withheld, and if you do, keep personal details out of the text and attachments.
Help with the portal is on 1300 305 695. The department's planner for the project is on 02 9995
5081, and EnergyCo's project line is 1800 061 114.
After exhibition, EnergyCo must answer the submissions in a Submissions Report, then the department assesses the project before the minister decides. We will report the number of submissions and EnergyCo's response when they are published.
Sources
Method. Researched and drafted with AI, straight from the primary sources below. Software matched 7 quotations exactly against our stored copies of their sources. How The Current works.
- EnergyCo, New England Renewable Energy Zone Network Infrastructure Project, Environmental Impact Statement, October 2026 (compressed) (PDF, 889 pages, read 9 November 2026): section 2 (page 19, strategic benefit payments); section 3 (PDF pages 102 to 117 and 146: hubs, camps, workforce); section 5 (Community and Employment Benefit Program); Table 10.6 (pages 395 to 400, social impact evaluation); Table 12.6 (page 503, landholders). Shown in Exhibits A and B.
- EnergyCo, EIS Executive Summary, October 2026 (PDF, read 9 November 2026): length, council areas, timing, biodiversity, social, visual, noise, traffic and bushfire findings.
- NSW Department of Planning, Housing and Infrastructure, Exhibition notice, extension (PDF, read 9 November 2026), and the original exhibition notice: dates, council areas, EPBC status and what a submission must include.
- NSW Planning Portal, New England REZ Transmission Project, SSI-74175972 (project page, read 9 November 2026): status, exhibition dates and the contact planner.
- NSW Department of Planning, Housing and Infrastructure, Benefit-Sharing Guideline, November 2024 (PDF, read 10 October 2026), section on projects the guideline does not cover.
- EnergyCo, Notice of application (PDF, read 9 November 2026): EnergyCo's contact line.
How we did this
We listed every attachment on the project's Planning Portal page and downloaded the executive summary, the compressed EIS and both exhibition notices on 9 November 2026. We read the executive summary in full and the EIS sections cited above; we did not read the 22 technical reports, which hold the detailed assessments behind these findings. Page numbers are the EIS's own, with the PDF page given in each exhibit. To check whether the EIS offers neighbours any payment, we searched the full text of the main EIS volume for neighbour, proximal and non-easement alongside payment and compensation; we found the strategic benefit payment only against host landholders, and neighbour agreements mentioned only for an approved wind farm. A technical report could say more, and we will correct this if it does. We did not contact EnergyCo or the department. No private landholder is named. The “our view” section is opinion based on the documents described.