When a solar farm, wind farm or battery is built in the Tamworth Regional area, the council negotiates a planning agreement with the developer for money that goes to the wider community. The rates have had the attention, here and in our piece on the council's conference motion. The draft policy councillors voted 9 to nil to exhibit on 27 October (resolution 304/26, according to the minutes) also changes the timetable, and that change works in the other direction.
What changes, and when the money arrives
The business paper describes the policy adopted in December 2023 as a lump sum equal to 1.5% of
a project's capital investment value, with 50% payable on commencement of construction and the remainder payable annually over the life of the development
.
The draft keeps the 1.5% as a target and adds a floor. It then says
25% of the Benefit Sharing Value is required to be made as an upfront payment
,
with the rest paid yearly over the duration of the project's operations
.
Its payment section is headed by the trigger: Upon the commencement of project operations
,
the developer must tell the council the date and Pay the upfront contribution (inclusive of GST) within 20 business days of the operational commencement date
.
The 2023 policy and the draft, side by side
How the council's own comparison table describes each, plus the draft's wording.
| Setting | 2023 policy | October 2026 draft |
|---|---|---|
| How much | 1.5% of capital investment value, CPI-adjusted | 1.5% of capital investment value as the target, with a minimum of $1,062.50 a megawatt a year for solar and $1,312.50 for wind, before CPI |
| First payment | 50%, at the start of construction | 25%, within 20 business days of operations beginning |
| The rest | Yearly over the life of the development | Yearly over the project's operating life, CPI-adjusted |
| Less upfront | Council supported upfront lump sums for early works | Allowed at the council's discretion, with more security |
| Security | Not expressly referenced | Required where the full value is not paid upfront; a bank guarantee or cash bond preferred |
The comparison table in the business paper records that the 2023 position supported upfront lump
sums for early works in affected communities. The draft lets the council take less upfront, at its discretion, if a developer can show the
public benefit and offers increased security arrangements under the Planning Agreement
.
Its general clause on variations also lets the amount paid upfront be varied case by case. Its
default, though, has no payment before operations. The report sets out the change in its table but
does not give a reason for it.
What it means for one project
An illustration, our arithmetic, before CPI. Take a hypothetical 100 MW solar farm paying the draft's minimum of $1,062.50 a megawatt a year, and assume a 30-year life: $106,250 a year, or $3,187,500 over the project. Under the draft, a quarter of that, $796,875, would arrive about a month after the farm started generating. Applying the 2023 timing to the same total, half, $1,593,750, would have been due when construction began. Under the draft the first payment comes after construction, and is a quarter of the total rather than half.
Who it reaches
The draft also widens its reach. It applies to projects in the Tamworth Regional area, and
A renewable energy project outside the Tamworth Regional LGA is also subject to this Policy, where impacts are expected on Tamworth Regional communities
.
It names wind farms, solar farms, batteries, pumped hydro and transmission. All of the council's
share is to be paid to it as a monetary contribution through a Renewable Energy Planning Agreement
,
with a separate First Nations contribution of 15% on top. Road repair, workforce accommodation and
neighbour agreements stay outside it, as separate obligations.
Our view
The rate increase is what Tamworth has asked the rest of NSW local government to back, and it is
the part most people will read. The timing change matters as much to the places that host these
projects, and it runs the other way. The council's own case for the 25% uplift is that
Concurrent projects can compete for road base, aggregates, concrete, plant, contractors and skilled employees
.
That competition is sharpest while projects are being built, and by default the draft moves the first
dollar to after that phase. Some construction impacts are dealt with by separate road and accommodation
obligations, which the draft keeps, so the gap is narrower than it first looks. Still, a policy
that asks for more money on the strength of construction-period pressure should say why its default now
collects nothing during construction. The exhibition is the place to ask, and the council should
explain the change before it adopts the policy.
What happens next
Resolution 304/26 puts the draft on exhibition for a minimum of 28 days
,
with a further report to consider submissions before councillors decide whether to adopt it. On the
morning of 4 November, eight days after the vote, the draft was not among the projects listed on
the council's Have Your Say site. We will report how to make a submission when it opens, and the
outcome when the council decides.
Sources
Method. Researched and drafted with AI, straight from the primary sources below. Software matched 10 quotations exactly against our stored copies of their sources. How The Current works.
- Tamworth Regional Council, Business paper, Ordinary Council Meeting, 27 October 2026 (PDF, read 23 October and 4 November 2026), item 6.4, pages 20 to 28: the 2023 policy as the report describes it, the draft's settings, and the comparison of the existing policy, the draft and the NSW Benefit Sharing Guideline.
- Tamworth Regional Council, Annexures, Ordinary Council Meeting, 27 October 2026, Part 5 (PDF, read 4 November 2026), Annexure 1 to item 6.4, council pages 1373 to 1386: the draft Tamworth Regional Renewable Energy Contributions Policy dated 16 October 2026, sections 5, 6.2, 6.3 and 7.
- Tamworth Regional Council, Minutes, Ordinary Council Meeting, 27 October 2026 (PDF, read 3 November 2026): item 6.4, resolution 304/26, the 9 to nil vote and the exhibition of at least 28 days.
- Tamworth Regional Council, Have Your Say (web page, read 4 November 2026): the projects open for comment.
How we did this
We downloaded the business paper and its annexures from the council's business papers page on 23 October 2026 and the minutes on 3 November. The draft policy is a scanned annexure without a text layer, so we rendered its pages and transcribed the clauses we quote, then checked each against the page image; the transcription is kept with our copies. The description of the 2023 policy is the business paper's; we did not read the 2023 policy itself. The 100 MW solar example is ours: 100 times the draft's minimum solar rate, times an assumed 30-year life, before CPI. It is an illustration, not a figure any project has agreed, and a real agreement can be negotiated above the minimum or towards the 1.5% target. We checked the Have Your Say site in a browser on the morning of 4 November. We did not contact the council. The “our view” section is opinion based on the documents described.