What the fee is, and who pays it
On 23 October 2026 the Minister for Energy declared an access scheme for the New England
Renewable Energy Zone. It decides which generators may connect to the zone's high-voltage
network, and when, and every project that connects pays a yearly fee to a state account, the
Scheme Financial Vehicle. EnergyCo, which designs and runs the scheme, said on the day that
the scheme will also
generate funding for the Community and Employment Benefit Program
.
Setting the fee falls to ASL, acting as the NSW Consumer Trustee, which must act in the
long-term financial interests of NSW electricity customers.
This first round covers only the existing network. One part is the early access allocation, for projects that already had a connection application with Transgrid or an EIS on public exhibition when the scheme was declared, and that will connect to the existing 330 kV lines before EnergyCo's new transmission is energised, which EnergyCo expects in 2032. The other is the 132 kV network, where there is no cap on connections and a project needs EnergyCo's consent, assessed mainly on its community engagement record. Fees for projects connecting to the new transmission line will be consulted on separately, if it is authorised.
| Component | 330 kV, early access, until the new line's benefits arrive | 330 kV, early access, after | 132 kV network |
|---|---|---|---|
| Community purpose | 1,809 | 1,809 | 1,809 |
| Employment purpose | 639 | 639 | 639 |
| Administration (EnergyCo's estimate) | 330 | 330 | 158 |
| Access rights benefits | none | 1,479 | none |
| Total | 2,778 | 4,257 | 2,606 |
The community and employment amounts are the Electricity Infrastructure Investment Regulation's minimums of $1,700 and $600 a megawatt a year, indexed at 0.625% a quarter from 1 July 2024 to match the South West REZ, as ASL's paper explains. The paper says there is no maximum. The extra $1,479 on the 330 kV lines, which switches on only when the new transmission's capacity benefits reach early access projects, is set to bring the total into line with the South West REZ fee. Some projects pay nothing at all: the scheme's exemptions include projects that held a network operator's offer to connect when it was declared, or that sign a long-term energy services agreement or a capacity investment scheme agreement by 31 December 2026 (or a Tender 10 capacity agreement by 31 May 2027).
Exhibit A · from the source
ASL proposes to set the Community Purpose component at the prescribed minimum amount of $1,700/MW per annum, plus indexation to ensure consistency with the South West REZ Access Scheme.
ASL does not propose to set the component above the prescribed minimum, other than to adjust it for inflation.
the New England REZ is not materially different from other REZs in a way that would justify requiring projects to make a higher contribution on a per MW basis.
This component is separate and additional to any relevant state voluntary planning agreements.
Where the community money goes
ASL sets the amount; it does not spend it. Its paper says EnergyCo
Administers Access Fees collected for community and employment purposes
,
and describes the community component as
intended to fund benefits for communities in and around the REZ that host the network infrastructure and generation and storage projects supported by the Access Scheme
.
EnergyCo's page for the New England Community and Employment Benefit Program says an initial
$60 million will go to
communities hosting renewable energy and transmission lines
.
Its consultation on how the program works closed on 18 September 2026, and the page says a
consultation feedback report
will be available soon
.
On 17 November it had not been published there.
This is a separate stream from the payments councils negotiate with each project. The state's Benefit Sharing Guideline caps those at $1,050 a megawatt a year for wind and $850 for solar, in 2024-25 dollars, and the money usually flows through planning agreements with the council. On a 100 MW wind farm on early access, the access fee's community component would be about $180,900 a year and its employment component about $63,900, against up to $105,000 a year under the guideline before indexation (our arithmetic). So for each megawatt of a wind or solar farm, the larger of the two community streams is the one EnergyCo runs, not the council.
What Walcha's draft reply says
Walcha Council holds an extraordinary meeting at 9am on 18 November 2026 with one report on
the agenda, from the general manager, recommending that councillors endorse a draft submission to ASL. The report says the council
can argue that the area the benefit program covers
should be defined before fees are set
,
and that fees
should be set by determining the budget required to achieve meaningful benefits within each community in the REZ, as opposed to attracting generators
.
The draft letter attached to the report goes further. It points out that the New England
transmission runs a long way outside the zone, about 100 km south from the zone's boundary to
Bayswater, unlike the Central-West Orana and South West zones, and says it is
still unclear whether the Community and Employment Benefit Program will be available to Councils and communities on the transmission path
.
ASL's own description of the network agrees on the geography: the 500 kV line from the zone's
southern boundary to Bayswater sits
outside the REZ geographic area
.
EnergyCo's transmission EIS lists eight council areas on the route, ending in the Upper Hunter,
Muswellbrook and Singleton.
The draft also asks that the employment amount be backed by evidence of what $600 a megawatt
would achieve in each council area, noting that small centres such as Walcha have less training
infrastructure; ASL's paper says its employment advisory committee advised that $600 a
megawatt a year would meaningfully contribute to workforce and training needs in the zone. And
it repeats requests the council says the final scheme did not take up: no exemptions for
projects well advanced in planning, independent checks of each developer's community
engagement, and a fresh assessment for any early access project that misses its connection
date. Its closing line: it is
difficult to escape the impression that the enabling of generation and infrastructure is charging ahead in a predetermined fashion, leaving disillusioned and disenfranchised communities in a hazy wake
.
The letter is a draft until councillors vote on it.
Our view
ASL's reasoning is coherent on its own terms. Its job is to set a fee in the interests of electricity customers, and a per-megawatt charge that matches the South West zone avoids pushing projects out of New England or into higher tender prices. On the evidence it gives, the minimum plus inflation is a defensible starting point for the level.
But Walcha has the order of events right. The fee is being fixed now, with a determination promised before the end of 2026, while the question of who the community money is for is EnergyCo's and still unanswered in public: its consultation closed on 18 September and the feedback report is not out. The one feature that plainly does set New England apart is the one Walcha names. ASL's own paper puts the 500 kV run to Bayswater outside the zone, about 100 km of line by Walcha's count, through Hunter council areas that the “in and around the REZ” description may or may not reach. That does not by itself prove the fee should be higher; it does mean “not materially different” needs an explanation that deals with it. ASL's statement of reasons should say how it weighed the out-of-zone line, and EnergyCo should publish the program's boundaries before the fee that pays for it is final, so that councils along the route can tell whether $1,809 a megawatt is meant to reach them.
ASL's consultation page links the approach paper and the submission form; submissions closed at 5pm AEDT on Thursday 19 November 2026, and may be published unless the submitter asked for confidentiality. We will report ASL's final determination, and what it says about the submissions, when it is published.
Updated 20 November 2026. Submissions closed on 19 November 2026, so we put the description, the standfirst and this paragraph into the past tense. Nothing else changed.
How measured · our arithmetic
| Input | Value | Where |
|---|---|---|
| Regulation minimums, community and employment | $1,700; $600 per MW a year | Approach paper, sections 3.3.1 and 3.4.1 |
| Indexation | 0.625% a quarter from 1 July 2024 | Approach paper, sections 3.3.2 and 3.4.2 |
| Indicative components at 1 January 2027 | $1,809; $639; $330; $1,479; $158 | Approach paper, Tables 1 and 2, page 4 |
| Guideline rates, wind and solar (2024-25 base, before CPI) | $1,050; $850 per MW a year | Benefit Sharing Guideline, November 2024, page 24 |
The arithmetic. From 1 July 2024 to 1 January 2027 is 10 quarters; 1.00625 to the power of 10 is 1.0643. 1,700 times 1.0643 is 1,809.3, and 600 times 1.0643 is 638.6, matching the paper's “~$1,809” and “~$639”. Totals: 1,809 + 639 + 330 = 2,778; plus 1,479 = 4,257; 1,809 + 639 + 158 = 2,606. For a 100 MW project: 100 times 1,809 is $180,900 a year, 100 times 639 is $63,900, and 100 times 2,778 is $277,800 in total before the step-up. Under the guideline, 100 times 1,050 is $105,000 for wind ($85,000 for solar), a ceiling before indexation. The 100 MW project is an illustration, not a real project; fees are charged on each project's maximum capacity in the access rights register.
Sources
Method. Researched and drafted with AI, straight from the primary sources below. Software matched 14 quotations exactly against our stored copies of their sources. How The Current works.
- AusEnergy Services Limited, New England Renewable Energy Zone Existing Network Access Fees: Approach Paper (PDF, 28 pages, October 2026, version 1 released 23 October 2026, read 17 November 2026): the fee tables (pages 4 and 19 to 23), scope (pages 7 to 13), the community and employment components (pages 15 and 16), access rights benefits (pages 17 and 18), exemptions (page 12) and timing (page 24). Shown in Exhibit A; inputs to panel B.
- AusEnergy Services Limited, Factsheet: New England REZ Access Fees, Existing Network (PDF, read 17 November 2026): the proposed amounts, indexation and the closing date.
- AusEnergy Services Limited, New England REZ Access Scheme Fees: Have your say (web page, read 17 November 2026): the consultation period, the 5pm AEDT closing time, the submission form and the note that submissions may be published.
- Walcha Council, Business Paper, Extraordinary Meeting of Council, 18 November 2026 (PDF, 7 pages, read 17 November 2026): item 3.1, Response to New England Renewable Energy Zone Access Fees consultation (pages 3 and 4), and attachment 1, the proposed response (pages 5 to 7).
- EnergyCo, New England Renewable Energy Zone Community and Employment Benefit Program (web page, read 17 November 2026).
- EnergyCo, Access scheme declared for New England Renewable Energy Zone (media release, 23 October 2026, read 17 November 2026).
- Minister for Energy, Renewable Energy Zone (New England) Access Scheme Order 2026, NSW Government Gazette 438, 23 October 2026 (PDF, read 17 November 2026).
- NSW Department of Planning, Housing and Infrastructure, Benefit Sharing Guideline (PDF, November 2024): the rates on page 24.
- EnergyCo, New England REZ Network Infrastructure Project, EIS Executive Summary, October 2026 (PDF, read 9 November 2026): the route's eight council areas.
How we did this
We found the consultation through Walcha Council's business paper for 18 November, then read ASL's approach paper and factsheet in full. ASL's website returned an error to our plain requests; we read its consultation page in a browser and downloaded the two PDFs it links. Walcha's draft submission is a scanned attachment with no text layer, so we read it from page images and quote it from our transcription. We read EnergyCo's program page and release, and the gazetted order. The 100 MW example and the indexation check are our arithmetic, shown in panel B. We did not contact ASL, EnergyCo or Walcha Council. The “our view” section is opinion based on the documents described.