If you swim at Warialda, the pool is open for the 2026-27 season. The council's swimming pool report in the 19 November business paper says the Bingara pool opened on Friday 2 October and Warialda's on Friday 23 October, with encouraging attendance since. The question is how many more seasons it has.

Item 9.6 on the agenda, from the council's Director of Business and Strategy, Justin Hellmuth, reports an inspection of the pool by a firm called Commercial Pool Consulting. Its 21-page report is attached to the item. The council's summary of it is blunt: the consultant considers the facility to be at the end of its useful life.

What the inspection found

The site has a six-lane, 50-metre pool and a toddlers' pool, built around 1965. The two share one balance tank, one circulation pump, the sand filters and the chemical dosing. The inspection found trouble in nearly all of it.

The walls. The gutter and hob walls along both long sides of the 50-metre pool show major cracking and corroding reinforcing steel, the report says, with some sections showing signs of breaking away from the main wall. Pieces of concrete that had already broken off were retrieved from the bottom of the pool. The toddlers' pool is in better shape after earlier works, but shows cracking and movement.

The leaks. The automatic top-up is broken, and the report says Staff are filling the pools every second day with large amounts of water. The consultant reads that as the pools losing large amounts of water and chemicals, at a high daily operating cost. The buried pipework is heavily corroded where it could be seen, and the wall between the deep end and the balance tank is believed to be cracked and leaking. Neither the tank nor the full run of pipe could be inspected, so the council's report says the extent of the leaks is still to be confirmed.

The plant. Both sand filter pits have cracking concrete walls. The pump is burning out its seals about every six months because the suction pipework is too small for it, the report says, and the return pipework is rusting, including under the plantroom floor. The consultant also found that the backwash and overflow discharge to stormwater rather than sewer, that the toddlers' pool lacks compliant handrails, and that there are finger, toe and hand entrapment points to fix.

Repair or replace

The consultant's answer is replace. On repairs, the report says There is NO benefit to spending money on these pools to fix or patch areas in the noted issues I have reviewed. Fixing the walls would leave the failing pipes, filter pits and plant in place, the council's report explains, and new plant would still need new pipework, because the existing pipes are too small. Its closing statement gives the pool, in its current state, a short lifeA.

Exhibit A · from the source

In closing and with the best to my knowledge from what I have been able to view / inspect the current Pool and equipment condition on site is so poor and unworkable in the long term to consider repairing. The Pools current condition is not compliant in multiple areas and at this stage I believe has a very shortened current life span. (1-2 Years approx.)

I would highly recommend the above recommendations be applied.

Quoted from the closing statement, page 21, of the Warialda Swimming Pool Inspection Report by Commercial Pool Consulting (attachment 1 to item 9.6, 19 November 2026 meeting), read 20 November 2026. Wording and punctuation as in the report. The marking is ours. Back to the summary

What it proposes instead is to demolish the pools and plantroom and build one new 50-metre lap pool of four to six lanes, 1.2 to 2.5 metres deep, with stairs and ramps for access, and to replace the toddlers' pool with a water play pad that has no pool structure and could be shut in the off-season. Its estimate is about $5 million to $5.5 million for the pool and $0.5 million to $0.6 million for the water play area, with a budget estimate of $6 million to $6.3 million. The council's report points out that the itemised figures add up to $5.5 million to $6.1 million, less than the headline estimate. The consultant itself says the number is not one to bank: A fully costed design for the new aquatic facilities should be completed and submitted before any construction budget is set.

What councillors were asked to do

The item was an information report, not a decision on the pool. Its recommendation was That Council receive and note the report on the condition of Warialda Swimming Pool and the further investigations outlined to inform consideration of its future replacement.

Those investigations are concept designs for two layouts: the consultant's 50-metre pool with a splash park, and a 25-metre pool with a splash park, which the council's report adds as an option to look at. The designs would show how each fits the site and serves schools, clubs and recreational swimmers, and would be costed, including demolition, plant, access, design fees and contingency. Concepts, costs and rough delivery timeframes would then come back to councillors to choose an option, with detailed design, approvals and tendering after that. The report gives no date for the concepts, does not price the 25-metre option, and does not say where the money for a replacement would come from. For scale, the council's September quarter budget review shows it expects $14.0 million from rates and annual charges in 2026-27; the consultant's estimate is roughly 43 to 45 per cent of that (our arithmetic).

The meeting was held at Bingara on Thursday 19 November. The minutes, which will record what councillors resolved, were not on the council's meeting portal when we checked on 20 November.

What the date on the report does not settle

The inspection report's cover gives the inspection date as Thursday, 15 October 2025. But 15 October fell on a Thursday in 2026, not 2025, and the file itself was created on 27 October 2026, so the year on the cover may be a slip. The council's report does not say when the inspection was done. If it was in October 2025, the one-to-two-year estimate began running a season earlier than it seems.

Our view

The council's report is a fair summary of the inspection in every respect but one: it leaves out the consultant's estimate that the pool has about one to two years left. That is the line a Warialda family, a swimming club or a school planning next year's carnival most needs, and it sits only on the last page of the attachment. It should be in the council's own words, alongside a plan for what happens if the pool cannot open one summer before a replacement is ready.

The consultant is also right that $6 million to $6.3 million is a starting estimate, and the council is right to cost a smaller 25-metre option before choosing. But set against the $14.0 million a year the shire budgets from rates and annual charges, this is not a project to fund from rates alone, and every funding conversation will start with a costed design. On the consultant's own estimate of the pool's life, the concept designs need a date, and soon.

We will report what councillors decided when the minutes are published, and the concept designs and costs when they come back to a council meeting.

Sources

Method. Researched and drafted with AI, straight from the primary sources below. Software matched 7 quotations exactly against our stored copies of their sources. How The Current works.

  1. Gwydir Shire Council, Warialda Pool Condition Report, Ordinary Council Meeting, 19 November 2026, item 9.6 (item ID 2026-684, 3 pages, read 20 November 2026): the recommendation, the council's summary of the inspection, the cost note and the proposed concept designs.
  2. Commercial Pool Consulting, Warialda Swimming Pool Inspection Report, attachment 1 to item 9.6 (21 pages, read 20 November 2026): the findings on the pools, pipework and plant (pages 3 to 19), the outcome and cost estimate (pages 19 and 20) and the closing statement (page 21). Shown in Exhibit A.
  3. Gwydir Shire Council, Ordinary Council Meeting agenda packet, 19 November 2026 (279 pages, Files tab, read 20 November 2026): the swimming pool report on opening dates (page 103, in the Business and Strategy report) and the September quarter budget review statement, rates and annual charges budget (page 132, item 9.7).
  4. Gwydir Shire Council meeting portal, meeting record for 19 November 2026 (checked 20 November 2026): no minutes file published.

How we did this

We read the council's report and the whole 21-page inspection report it attaches, and the parts of the business paper on the pool season and the budget, all from the council's meeting portal. The officer's report was not in the agenda packet, so we fetched it and the attachment as separate files from the portal. Quotations are from the documents' text layers, with page numbers counted from the start of each PDF; the inspection report prints its own matching page numbers. The share of rates income is our arithmetic: $6.0 million and $6.3 million divided by the $14.011 million the budget review shows for rates and annual charges in 2026-27. The note on the inspection date compares the date on the report's cover with the calendar and with the PDF file's creation date. The minutes of the 19 November meeting were not published when we wrote this, so we report what councillors were asked to do, not what they decided. We name the consulting firm but not its staff. We did not contact the council for this piece. The “our view” section is opinion based on the documents described.